Client:
Kategorie: Switch room, Critical infrastructures.
New energy control room puts competence at the center

JST control room concept: The new control room of INGAVER GmbH in Bremen is characterised by carefully thought-out spatial planning with integrated air conditioning and lighting system; a future-oriented joint project of the companies swb Erzeugung and ArcelorMittal Bremen, in which synergy effects are to be used to optimise the energy supply.
Four control rooms on a company site. Managed by two companies that cooperate with each other to optimise the energy supply for steel production on the Weser. What could be more obvious than an alliance? “In the past we have always been interested in close cooperation. That is why we are joining forces at this point”, explains INGAVER Energy Manager Thorsten Doege the joint path taken by swb and ArcelorMittal Bremen.
Central energy control room as a first step
As the first step of the new company, four distributed control rooms were combined into one central control room. From here, the operating team can organise and manage all energy media on site – such as electricity, water, technical gases and compressed air. swb CEO Dr. Torsten Köhne calls the merger and with it the new control room “an important step towards future-oriented sustainable steel production.”
Ergonomic requirements for technology and furniture
Technology and furniture in the new energy control room should also be “forward-thinking.” A requirement that the control room professionals at JST have fully met. Project manager Thorsten Doege comments: “Previously, each individual employee had to monitor around 20 screens arranged in two rows. Something urgently needed to be done.”
Workstation in control room with height-adjustable desk.
Individual adjustment possible at the workplace
The solution: large-display technology. Today, each operator uses six displays at his workstation and six more displays on the Video Wall. The ergonomics in the energy control room were additionally optimised by height-adjustable desks and special 24/7 chairs.
Representative control room
The employees also rate the INGAVER control room as thoroughly positive. They were involved in the planning at an early stage of the project. Made possible by virtual tours thanks to photo-realistic 3D plans, produced by the JST specialists.
Praise for quality of advice and cooperation
For the energy manager one thing is certain: “The cooperation with JST ran perfectly from the first visit to the control room simulator all the way up to its completion.”
New control room for INGAVER
You are currently viewing a placeholder content from YouTube. To access the actual content, click the button below. Please note that doing so will share data with third-party providers.
More Information